Name of Project | Location | Amount (P) | Source of Funds | Date Started | Date Finished | Remarks |
---|
Repair of Pavilion Stage | Poblacion | 22,800.00 | 20% EDF | | | for bidding |
Repair of Auditorium Backstage | Poblacion | 87,067.97 | 20% EDF | | | For negotiation |
Repainting of Mayor’s Office | Poblacion | 48,880.00 | 20% EDF | | | for bidding |
Landscaping (of various Municipal Facilities) | Poblacion | 720,000.00 | 20% EDF | 5-Nov | | 85% accomp. |
Painting of Public Cemtery fence | San Roque | 18,280.00 | 20% EDF | | | For negotiation |
Repainting of TG-56 EWT | Sto Domingo | 121,969.13 | 20% EDF | | | for bidding |
Repainting of MRF Fence and Roof repair | Poblacion | 23,785.00 | 20% EDF | | | finished |
Electrical Fixture Installation at “Bahay Pagasa” Building | Poblacion | 4,535.00 | 20% EDF | | | finished |
Concepcion Road Concreting | San Roque | 388,483.40 | General fund | | | For negotiation |
SWIP | Dona Carmen | 2,027,181.96 | BUB Project | 13-06-16 | | 90% finished |
CONSTRUCTION OF LEARNING CENTER BLDG | Suaverdez | 262,867.61 | General fund | 20-08-16 | 08-11-16 | 30% finished |
CONSTRUCTION OF VERMIBEDS WITH SHED | Various | 718,713.86 | BUB Project | 20-08-16 | 08-11-16 | 50% finished |
EXPANSION OF LEVEL Ill WATER SUPPLY SYSTEM | Various | 6,438,079.97 | 20% EDF | 21-12-16 | | 75% accomp. |
CONSTRUCTION OF PASALUBONG CENTER | Poblacion | 800,000.00 | 20% EDF | 21-12-16 | | 40% accomp. |
PUBLIC MARKET IMPROVEM ENT | Poblacion | 2,700,000.00 | 20% EDF | | | To start early nest year |